 GPD3 - Concentrator: Ball bins, Ball Mill, and SAG Mill foundation, Nov 2011
|
 GDP3 - Moly building, Nov 2011
|
 GDP3 - Moly building (right), Concentrator (center), Nov 2011
|
 GDP3 - Moly building (right), Concentrator (center), Nov 2011
|
 GDP3 - Concentrator Site Preparation
|
 GDP3 - Pouring Moly Building Foundation
|
 GDP3 - Pouring Moly Building Foundation
|
.jpg) GDP3 - Pouring Moly Building Foundation
|
 GDP3 Site Overview
|
 GDP3 Moly Building Footings, Aug 2011
|
 GDP3 Partially Demolished Fine Ore Stockpile, Aug 2011
|
 GDP3 Partially Demolished Fine Ore Stockpile, July 2011
|
 Gibraltar Arial, Sept 2011
|
 Gibraltar Arial, Sept 2011
|
 GDP3: Preparations for demolition of the Fine Ore Stockpile, July 2011
|
 GDP3: Preparations for demolition of the Fine Ore Stockpile, July 2011
|
 Bucyrus Bucyrus 495 HR 60 Yard Shovel and Terex Haul Trucks |
 Bucyrus 495 HR 60 Yard Shovel and Terex Haul Truck Bucyrus 495 HR 60 Yard Shovel and Terex Haul Truck |
 Grantite Pit The Granite Pit |
 Komatsu 320 Haul Truck Komatsu 320 Haul Truck |
 SAG Mill SAG Mill |
 SAG Mill SAG Mill |
 Gibraltar's new primary crusher being commissioned
|
 Gibraltar's new primary crusher/conveyor system
|
 Gibraltar's new conveyor system from in-pit crusher to mill
|
 Construction of Gibraltar's new, in-pit primary crusher
|
 Gibraltar's new P&H 4100 shovel being commissioned
|
 October 2/07 -- Assembly of the SAG mill
|
 October 1/07 -- Assembly of the SAG mill
|
 September 27/07 -- Assembly of the SAG mill
|
 September 14/07 -- Arrival of the SAG mill components to Gibraltar
|
 August 21 - Construction of high angle conveyor belt which will feed ore to the SAG mill, fine ore bin in the background
|
 August 21 - Five new copper cleaner float cells, in the process of being installed
|
 August 15 - The SAG mill shells, loaded and departing Europe for Montreal.
|
 August 13 - Inside the SAG mill facility, preparations for the SAG mill installation are well underway
|
 August 13 - The SAG mill shells, at the Port in Europe being prepared for loading
|
 August 5 - Key SAG mill component, the ring gear, loaded in the hold, ready for shipping from Europe
|
 July 31 - Installing the trunions that will support the SAG mill
|
 July 31 - The near complete SAG mill building
|
 July 21 - The recently completed flotation circuit, 10 new, 160 m3 cells, operating as of mid-July
|
 June 30 - Loading of key SAG mill components in Rotterdam
|
 May/07 - SAG Mill building construction and installation of the crane. T his building, which will house the SAG Mill, is over 16,000 square feet in size and 80 feet high.
|
 April/07 -- Phase 2 of the concentrator modernization is the installation of 4 new float cells.
|
 Feb/07 -- Concrete forms in preparation for an upcoming pour
|
 Feb/07 -- erecting forms at the SAG mill building
|
 Feb/07 -- Key SAG mill components, currently being fabricated and assembled in Spain
|
 Feb/07 -- Key SAG mill components, currently being fabricated and assembled in Spain
|
 February/07 -- Current mining operations, Pollyanna Pit
|
 February/07 -- Granite Lake Pit -- stripping operations restarted in this pit in September 2006
|
 Jan/07 -- First copper cathode being harvested from the restarted SX-EW plant at Gibraltar
|
 Jan/07 -- First copper cathode being harvested from the restarted SX-EW plant at Gibraltar
|
 Jan/07 -- First copper cathode being harvested from the restarted SX-EW plant at Gibraltar
|
 Fine ore bin
|
 Gibraltar Mine
|
 MT 3700 205 ton haul truck
|
 Overhead view of Gibraltar mine, Granite Lake pit in foreground
|
 October/06 -- Laying the foundation for the SAG mill
|
 October/06 -- Laying the foundation for the SAG mill
|
 September/06 -- Breaking ground on the mill expansion project
|
 August/06 -- Construction of the first of ten, new float cells
|
 May/06 -- Laying the foundation for the first float cell
|
 March/04 -- Assembly of one of the new, Terex MT3700, 205 ton trucks purchased for the restart in 2004
|
 March/04 -- Assembly of the new P&H 2800XPB shovel, purchased for the restart of Gibraltar in 2004
|
 April/07 -- Construction of the building which will house the SAG mill
|
 April/07 -- Construction of the building which will house the SAG mill
|
 Feb/07 -- SAG mill discharge screen, awaiting shipment to Gibraltar from Pennsylvania
|
 February/07 -- Original flotation circuit, 96 cells in 3 banks to be replaced with 10 state-of-the-art float cells.
|
 GDP3 Construction - Preparations for demolition of the Fine Ore Stockpile
|
 GDP3 Moly Building Foundations, Sept 2011
|