GPD3 - Concentrator: Ball bins, Ball Mill, and SAG Mill foundation, Nov 2011

GDP3 - Moly building, Nov 2011

GDP3 - Moly building (right), Concentrator (center), Nov 2011

GDP3 - Moly building (right), Concentrator (center), Nov 2011

GDP3 - Concentrator Site Preparation

GDP3 - Pouring Moly Building Foundation

GDP3 - Pouring Moly Building Foundation

GDP3 - Pouring Moly Building Foundation

GDP3 Site Overview

GDP3 Moly Building Footings, Aug 2011

GDP3 Partially Demolished Fine Ore Stockpile, Aug 2011

GDP3 Partially Demolished Fine Ore Stockpile, July 2011

Gibraltar Arial, Sept 2011

Gibraltar Arial, Sept 2011

GDP3: Preparations for demolition of the Fine Ore Stockpile, July 2011

GDP3: Preparations for demolition of the Fine Ore Stockpile, July 2011

Bucyrus
Bucyrus 495 HR 60 Yard Shovel and Terex Haul Trucks

Bucyrus 495 HR 60 Yard Shovel and Terex Haul Truck
Bucyrus 495 HR 60 Yard Shovel and Terex Haul Truck

Grantite Pit
The Granite Pit

Komatsu 320 Haul Truck
Komatsu 320 Haul Truck

SAG Mill
SAG Mill

SAG Mill
SAG Mill

Gibraltar's new primary crusher being commissioned

Gibraltar's new primary crusher/conveyor system

Gibraltar's new conveyor system from in-pit crusher to mill

Construction of Gibraltar's new, in-pit primary crusher

Gibraltar's new P&H 4100 shovel being commissioned

October 2/07 -- Assembly of the SAG mill

October 1/07 -- Assembly of the SAG mill

September 27/07 -- Assembly of the SAG mill

September 14/07 -- Arrival of the SAG mill components to Gibraltar

August 21 - Construction of high angle conveyor belt which will feed ore to the SAG mill, fine ore bin in the background

August 21 - Five new copper cleaner float cells, in the process of being installed

August 15 - The SAG mill shells, loaded and departing Europe for Montreal.

August 13 - Inside the SAG mill facility, preparations for the SAG mill installation are well underway

August 13 - The SAG mill shells, at the Port in Europe being prepared for loading

August 5 - Key SAG mill component, the ring gear, loaded in the hold, ready for shipping from Europe

July 31 - Installing the trunions that will support the SAG mill

July 31 - The near complete SAG mill building

July 21 - The recently completed flotation circuit, 10 new, 160 m3 cells, operating as of mid-July

June 30 - Loading of key SAG mill components in Rotterdam

May/07 - SAG Mill building construction and installation of the crane. T his building, which will house the SAG Mill, is over 16,000 square feet in size and 80 feet high.

April/07 -- Phase 2 of the concentrator modernization is the installation of 4 new float cells.

Feb/07 -- Concrete forms in preparation for an upcoming pour

Feb/07 -- erecting forms at the SAG mill building

Feb/07 -- Key SAG mill components, currently being fabricated and assembled in Spain

Feb/07 -- Key SAG mill components, currently being fabricated and assembled in Spain

February/07 -- Current mining operations, Pollyanna Pit

February/07 -- Granite Lake Pit -- stripping operations restarted in this pit in September 2006

Jan/07 -- First copper cathode being harvested from the restarted SX-EW plant at Gibraltar

Jan/07 -- First copper cathode being harvested from the restarted SX-EW plant at Gibraltar

Jan/07 -- First copper cathode being harvested from the restarted SX-EW plant at Gibraltar

Fine ore bin

Gibraltar Mine

MT 3700 205 ton haul truck

Overhead view of Gibraltar mine, Granite Lake pit in foreground

October/06 -- Laying the foundation for the SAG mill

October/06 -- Laying the foundation for the SAG mill

September/06 -- Breaking ground on the mill expansion project

August/06 -- Construction of the first of ten, new float cells

May/06 -- Laying the foundation for the first float cell

March/04 -- Assembly of one of the new, Terex MT3700, 205 ton trucks purchased for the restart in 2004

March/04 -- Assembly of the new P&H 2800XPB shovel, purchased for the restart of Gibraltar in 2004

April/07 -- Construction of the building which will house the SAG mill

April/07 -- Construction of the building which will house the SAG mill

Feb/07 -- SAG mill discharge screen, awaiting shipment to Gibraltar from Pennsylvania

February/07 -- Original flotation circuit, 96 cells in 3 banks to be replaced with 10 state-of-the-art float cells.

GDP3 Construction - Preparations for demolition of the Fine Ore Stockpile

GDP3 Moly Building Foundations, Sept 2011