August 13 - Inside the SAG mill facility, preparations for the SAG mill installation are well underway 51 KB, approx. 10 seconds at 56.6Kbps |
|
August 13 - The SAG mill shells, at the Port in Europe being prepared for loading 47 KB, approx. 10 seconds at 56.6Kbps |
|
August 5 - Key SAG mill component, the ring gear, loaded in the hold, ready for shipping from Europe 51 KB, approx. 11 seconds at 56.6Kbps |
|
July 31 - Installing the trunions that will support the SAG mill 71 KB, approx. 14 seconds at 56.6Kbps |
|
July 31 - The near complete SAG mill building 59 KB, approx. 12 seconds at 56.6Kbps |
|
July 21 - The recently completed flotation circuit, 10 new, 160 m3 cells, operating as of mid-July 37 KB, approx. 8 seconds at 56.6Kbps |
|
June 30 - Loading of key SAG mill components in Rotterdam 31 KB, approx. 7 seconds at 56.6Kbps |
|
May/07 - SAG Mill building construction and installation of the crane. T his building, which will house the SAG Mill, is over 16,000 square feet in size and 80 feet high. 122 KB, approx. 24 seconds at 56.6Kbps |
|
April/07 -- Phase 2 of the concentrator modernization is the installation of 4 new float cells. 30 KB, approx. 7 seconds at 56.6Kbps |
|
April/07 -- Construction of the building which will house the SAG mill 29 KB, approx. 6 seconds at 56.6Kbps |
|
April/07 -- Construction of the building which will house the SAG mill 20 KB, approx. 5 seconds at 56.6Kbps |
|
February/07 -- Original flotation circuit, 96 cells in 3 banks to be replaced with 10 state-of-the-art float cells. 36 KB, approx. 8 seconds at 56.6Kbps |