TSX: TKO   $5.22   +0.22      NYSE Amex: TGB   $5.09   +0.20
Building wealth through developing and operating major copper mines
Gibraltar

Photo Gallery
Gibraltar - Taseko's Foundation for Growth

A key component of Taseko's growth strategy is the expansion and modernization of its wholly owned Gibraltar mine. The goal is to create an operation with a mid-tier cost profile that is able to generate positive cash flow at all points of the copper price cycle.

Mine Expansion

Gibraltar is undergoing a major, multi-phase expansion and modernization program. Over the last two years, approximately $250 million has been invested at Gibraltar in both mining equipment and concentrator upgrades. By the end of 2010, Gibraltar's annual production capacity will increase to 115 million pounds of copper and 1.4 million pounds of molybdenum.

The Phase I & II expansion and modernization programs included the addition of a new 34 foot semi-autogenous grinding (SAG) mill, a complete replacement of the original flotation recovery system as well as a number of downstream upgrades and modifications.

Gibraltar OverheadPhase I was completed, on time and on budget, in early 2008 and the new equipment is being commissioned with ramp up continuing through 2009. During the ramp up, production levels are expected to steadily increase with expected annualized capacity reaching 100 million pounds of copper. Total cost for the Phase I expansion was $76 million.

Phase II modifications will allow the new SAG mill to process up to its designed capacity of 55,000 tons per day (tpd) by increasing capacity in other circuits of the concentrator. The expansion project will include the addition of an upgraded tailings pumping system, increased regrind capacity, cleaner flotation cells, pressure filters and driers. Phase II is targeted for completion in early 2010. Commissioning and ramp up of Phase II is expected to take place in 2010 until annualized production rates of 115 million pounds of copper are achieved. As of mid 2009, approximately $20 million was left to spend on Phase II.


Extending Mine Life

Over the past three years, Taseko has spent in excess of $20 million to expand Gibraltar's reserves and resources. When Gibraltar was restarted in 2004, the proven and probable reserves were 149 million tons and the mine life was 12 years. Today, the mine life is 25+ years following the most recent reserve update in December 2008.

Gibraltar Reserves and Resources at December 31, 2008

Category
(at 0.20% Cu Cut-off)
Size
(Million Tons)
Grade Recoverable Metal Contained Metal
Cu (%) Mo (%) Cu (Billions lbs) Cu (Billions lbs)
Proven & Probable Reserves 472 0.315 0.008 2.7 3.0
Measured & Indicated Resources 959 0.298 0.008 - 5.7

The mineral resource and reserve estimations were completed by Gibraltar mine staff under the supervision of Scott Jones, P.Eng., Vice-President, Engineering and a Qualified Person under National Instrument 43-101. Mr Jones has verified the methods used to determine grade and tonnage in the geological model, reviewed the long range mine plan, and directed the updated economic evaluation. The estimates for the Gibraltar Extension used long term metal prices of US$1.75/lb for copper and US$10.00/lb for molybdenum and a foreign exchange of C$0.82 per US dollar while the estimates for the balance of the reserves used long term metal prices of US$1.50/lb for copper and US$10.00/lb for molybdenum and a foreign exchange of C$0.80 per US dollar. Mr Jones has reviewed this release. A technical report will be filed on www.sedar.com.


Operations

The following table is a summary of the operating statistics for Gibraltar Mine:

Q1
2009
Fiscal
20081
Fiscal
2007
Total tons mined (millions)² 6.9 51.8 35.4
Tons of ore milled (millions) 3.2 13.6 9.5
Stripping ratio 1.0 2.7 2.6
Copper grade (%) 0.368 0.351 0.328
Molybdenum grade (%Mo) 0.010 0.009 0.011
Copper recovery (%) 82.3 75.8 77.5
Molybdenum recovery (%) 30.8 31.8 29.6
Copper production (millions lb) 19.9 76.9 51.8
Molybdenum production (thousands lb) 187 840 580
Copper production costs, net of by product credits³, per lb of copper US$0.90 US$1.87 US$1.03
Off property costs for transport, treatment (smelting & refining) & sales per lb of copper US$0.28 US$0.43 US$0.35
Total cash costs of production per lb of copper US$1.18 US$2.30 US$1.38


1 Fiscal 2008 relates to the 15 months ending December 31, 2008.

2 Total tons mined includes sulphide ore, oxide ore, low grade stockpile material, overburden, and waste rock which were moved from within pit limit to outside pit limit during the period.

3 The by-product credit is based on pounds of molybdenum and ounces of silver sold. Unit costs were lower in fiscal 2005 because molybdenum prices and pounds of copper produced were higher.

4 Cash costs of production is a non-GAAP measure. This non-GAAP measure is intended to provide additional information to investor and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with GAAP. Cash costs of production is a common performance measure in the copper industry and includes direct cost of operations and related costs through to refined metal.

Site Statistics

The Gibraltar mine site covers approximately 109 square kilometres and consists primarily of 251 mineral claims and 30 mining leases. The property hosts resources and reserves in seven separate mineralized zones which has supported mining for most of the past 30 years.

Gibraltar is located in an area with well-developed infrastructure. The property is accessible by a combination of highways and paved roads, and it is close to a rail network that provides service for shipment of copper concentrates through the Pacific Ocean port of North Vancouver. The mine is a 45-minute drive from local communities that provide goods, services and personnel.


Forward Looking Statements

The above information includes certain statements that may be deemed "forward-looking statements". Investors are cautioned that any such statements are not guarantees of future performance and actual results or developments may differ materially from those projected in the forward-looking statements. For more information on the risks inherent in the Company's business, Investors should review the Company's annual Form 20-F filing with the United States Securities and Exchange Commission and its home jurisdiction filings that are available at www.sedar.com.